Major roadwork projects across the state have been stopped or slowed down because of a contract dispute between Local 324 Operating Engineers and the Michigan Infrastructure and Transportation Association.

In a press release, MITA said that they have tried to negotiate with the Local 324 and they have refused.

MITA said because of that they will, “stand together as a unified front against these coercive actions by the union and the union’s refusal to negotiate and has initiated a defensive lockout of all OE 324 employees." 

Below is a list of projects affected in metro Detroit

Oakland County

Projects that are shut down

  • Pine Tree resurfacing in Orion Twp.
  • Dequindre widening reconstruction, Long Lake to Burning Bush in Troy/Sterling Heights
  • Opdyke bridge replacement over Clinton River in Auburn Hills
  • Adams Rd. resurfacing, Square Lake to South Blvd. in Bloomfield Twp. and Troy
  • Tripp Road reconstruct, Dixie Highway to Van in Groveland Twp.
  • Baldwin widening/reconstruct, Gregory to Waldon in Orion Twp.
  • Walton Blvd. culvert replacements and resurfacing, Adams to Squirrel in Rochester Hills and Auburn Hills

Projects that are ongoing but could be shut down

  • South Blvd., Adams to Crooks resurfacing in Rochester Hills/Troy
  • Wixom Road bridge replacement over Huron River in Commerce Township
  • Secord Lake Road bridge preventative maintenance in Addison Township

Projects scheduled to start this week but may be shut down

  • Grand River intersection with South Hills,  intersection widening in Lyon Township
  • Orion/Flint/Miller intersection roundabout construction in Orion Twp.

Macomb County

Projects that are shut down

  • Projects which were started but are now suspended:
  • Mound Road from 14 Mile to 18 Mile RRR resurfacing
  • Van Dyke from 18 Mile to Clinton River bridge RRR resurfacing
  • 2018 concrete PPP various locations countywide

Projects that have not been started

  • 2018 HMA PPP county wide, including resurfacing on Mound south of 14 Mile
  • Metro Parkway/ Garfield Road RRR resurfacing
  • Utica Road from Dodge Park to Schoenherr HMA resurfacing with passing lanes at selected locations
  • Clinton Twp SAD subdivision reconstruction projects

Projects which will be bid by Sept. 7 and may be impacted

  • 23 Mile from North Avenue to Fairchild road reconstruction and widening
  • Macomb Orchard Trail from East Pond Creek to Powell Road rehabilitation

Projects which were bid and will proceed or are currently under construction

  • 2018 HMA PPP county wide, including resurfacing on Mound south of 14 Mile
  • Metro Parkway/ Garfield Road RRR resurfacing
  • Utica Road from Dodge Park to Schoenherr HMA resurfacing with passing lanes at selected locations